US Army Corps of Engineers

Green Peter Dam

December 2025

Day of MonthTotal Generation MWhAverage Generation MWStation Use MWhInflow cfsTotal Outflow cfsGeneration Flow cfsSpill cfsMidnight Reservoir ElevationAverage Forebay ElevationAverage Tailwater ElevationAverage Head feetMidnight Storage kaf
1 716 700 782.49 782.55 695.34 87.21 5910.37
2 593 650 781.86 782.22 695.18 87.04 5730.27
3 495 650 780.53 781.23 695.15 86.08 5363.93
4 420 650 779.11 779.66 695.09 84.57 4990.97
5 1934 1790 793.74 784.09 697.86 86.23 9891.79
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
TOT            
AVG    832 888   783.55 781.95 695.72 86.23 6377.47
MAX    1934 1790   793.74 784.09 697.86 87.21 9891.79
MIN    420 650   779.11 779.66 695.09 84.57 4990.97