US Army Corps of Engineers

Hungry Horse Dam

Friday February 13, 2026

New Date:

HourTotal Outflow kcfsGeneration Flow kcfsSpill kcfsForebay ElevationTailwater ElevationAverage Head
1 1.20 1.20 0.00 3539.00 3073.51 465.49
2 1.20 1.20 0.00 3539.02 3073.44 465.58
3 1.20 1.20 0.00 3539.01 3073.46 465.55
4 1.20 1.20 0.00 3539.01 3073.47 465.54
5 1.20 1.20 0.00 3539.00 3073.47 465.53
6 1.20 1.20 0.00 3539.03 3073.48 465.55
7 1.20 1.20 0.00 3539.03 3073.48 465.55
8 1.20 1.20 0.00 3539.02 3073.44 465.58
9 1.20 1.20 0.00 3539.03 3073.46 465.57
10 1.20 1.20 0.00 3539.03 3073.48 465.55
11
12
13
14
15
16
17
18
19
20
21
22
23
24
AVG 1.20 1.20 0.00 3539.02 3073.47 465.55
MAX 1.20 1.20 0.00 3539.03 3073.51 465.58
MIN 1.20 1.20 0.00 3539.00 3073.44 465.49