HourTotal Outflow cfsGeneration Flow cfsSpill cfsForebay ElevationTailwater ElevationAverage Head
1 2912 1860.40 1551.50 308.90
2 2912 1860.41 1551.50 308.91
3 2927 1860.41 1551.50 308.91
4 2897 1860.41 1551.50 308.91
5 2897 1860.41 1551.50 308.91
6 2897 1860.41 1551.50 308.91
7 2932 1860.41 1551.50 308.91
8 2920 1860.41 1551.50 308.91
9 2938 1860.41 1551.50 308.91
10 2938 1860.41 1551.50 308.91
11 2987 1860.41 1551.50 308.91
12 2990 1860.40 1551.50 308.90
13 2990 1860.40 1551.50 308.90
14 3040 1860.40 1551.50 308.90
15 3070 1860.40 1551.50 308.90
16 3058 1860.39 1551.50 308.89
17 3058 1860.39 1551.50 308.89
18 3046 1860.39 1551.50 308.89
19 3046 1860.39 1551.50 308.89
20 3003 1860.38 1551.50 308.88
21 2973 1860.38 1551.50 308.88
22 2961 1860.38 1551.50 308.88
23 2930 1860.38 1551.50 308.88
24 2933 1860.37 1551.50 308.87
AVG 2969   1860.40 1551.50 308.90
MAX 3070   1860.41 1551.50 308.91
MIN 2897   1860.37 1551.50 308.87