| Hour | Total Outflow kcfs | Generation Flow kcfs | Spill kcfs | Forebay Elevation | Tailwater Elevation | Average Head |
| 1 | 184.40 | 59.60 | 123.90 | 265.02 | 159.52 | 105.50 |
| 2 | 185.20 | 60.30 | 123.90 | 265.02 | 159.79 | 105.23 |
| 3 | 187.20 | 60.60 | 123.90 | 265.02 | 159.62 | 105.40 |
| 4 | 186.50 | 59.90 | 123.90 | 264.92 | 159.82 | 105.10 |
| 5 | 184.80 | 60.00 | 123.90 | 264.92 | 159.82 | 105.10 |
| 6 | 184.70 | 59.80 | 123.90 | 264.92 | 160.02 | 104.90 |
| 7 | 184.00 | 59.20 | 123.90 | 265.02 | 160.22 | 104.80 |
| 8 | 184.10 | 59.30 | 123.90 | 265.02 | 160.22 | 104.80 |
| 9 | 184.30 | 59.50 | 123.90 | 265.02 | 160.22 | 104.80 |
| 10 | 185.60 | 58.90 | 123.90 | 265.02 | 160.52 | 104.50 |
| 11 | 184.40 | 59.60 | 123.90 | 265.02 | 160.81 | 104.21 |
| 12 | 186.30 | 59.60 | 123.90 | 265.02 | 160.72 | 104.30 |
| 13 | 184.80 | 59.90 | 123.90 | 264.92 | 160.91 | 104.01 |
| 14 | | | | | | |
| 15 | | | | | | |
| 16 | | | | | | |
| 17 | | | | | | |
| 18 | | | | | | |
| 19 | | | | | | |
| 20 | | | | | | |
| 21 | | | | | | |
| 22 | | | | | | |
| 23 | | | | | | |
| 24 | | | | | | |
|
| AVG | 185.10 | 59.71 | 123.90 | 264.99 | 160.17 | 104.82 |
|
| MAX | 187.20 | 60.60 | 123.90 | 265.02 | 160.91 | 105.50 |
| MIN | 184.00 | 58.90 | 123.90 | 264.92 | 159.52 | 104.01 |