Green Peter Dam
Wednesday July 15, 2026
| Hour | Total Outflow cfs | Generation Flow cfs | Spill cfs | Forebay Elevation | Tailwater Elevation | Average Head |
| 1 | 50 | | | 946.70 | 692.04 | 254.66 |
| 2 | 50 | | | 946.70 | 692.02 | 254.68 |
| 3 | 50 | | | 946.70 | 692.01 | 254.69 |
| 4 | 50 | | | 946.70 | 692.01 | 254.69 |
| 5 | 50 | | | 946.71 | 692.01 | 254.70 |
| 6 | 50 | | | 946.71 | 692.00 | 254.71 |
| 7 | 50 | | | 946.72 | 692.01 | 254.71 |
| 8 | 50 | | | 946.72 | 692.00 | 254.72 |
| 9 | 50 | | | 946.71 | 692.00 | 254.71 |
| 10 | 50 | | | 946.71 | 692.01 | 254.70 |
| 11 | 50 | | | 946.71 | 692.00 | 254.71 |
| 12 | 50 | | | 946.71 | 692.00 | 254.71 |
| 13 | 50 | | | 946.72 | 692.00 | 254.72 |
| 14 | 50 | | | 946.71 | 695.90 | 250.81 |
| 15 | 1900 | | | 946.68 | 698.44 | 248.24 |
| 16 | 1900 | | | 946.62 | 698.51 | 248.11 |
| 17 | 1900 | | | 946.57 | 698.58 | 247.99 |
| 18 | 1900 | | | 946.51 | 698.58 | 247.93 |
| 19 | 1900 | | | 946.46 | 698.52 | 247.94 |
| 20 | 1850 | | | 946.39 | 698.56 | 247.83 |
| 21 | 1900 | | | 946.33 | 698.52 | 247.81 |
| 22 | 1860 | | | 946.28 | 698.23 | 248.05 |
| 23 | 50 | | | 946.27 | 692.20 | 254.07 |
| 24 | 50 | | | 946.27 | 692.05 | 254.22 |
|
| AVG | 663 | | | 946.60 | 694.34 | 252.25 |
|
| MAX | 1900 | | | 946.72 | 698.58 | 254.72 |
| MIN | 50 | | | 946.27 | 692.00 | 247.81 |