US Army Corps of Engineers

Lookout Point Dam

Tuesday August 4, 2026

New Date:

HourTotal Outflow cfsGeneration Flow cfsSpill cfsForebay ElevationTailwater ElevationAverage Head
1 0 861.74 693.50 168.24
2 0 861.77 693.35 168.42
3 0 861.79 693.19 168.60
4 0 861.81 693.02 168.79
5 0 861.84 692.86 168.98
6 0 861.87 692.69 169.18
7 0 861.88 692.53 169.35
8 0 861.90 692.37 169.53
9 0 861.93 692.20 169.73
10 0 861.94 692.04 169.90
11 0 861.96 691.88 170.08
12 0 861.98 691.71 170.27
13 0 861.98 691.99 169.99
14 3900 861.90 692.06 169.84
15 3900 861.80 692.25 169.55
16 3900 861.73 692.20 169.53
17 3000 861.66 692.33 169.33
18 5710 861.52 692.58 168.94
19 5750 861.39 692.94 168.45
20 5690 861.30 693.27 168.03
21 5880 861.12 693.60 167.52
22 5330 861.00 693.73 167.27
23 0 861.00 693.93 167.07
24 0 861.04 693.82 167.22
AVG 1794   861.66 692.75 168.91
MAX 5880   861.98 693.93 170.27
MIN 0   861.00 691.71 167.07