US Army Corps of Engineers

Foster Dam

Saturday May 3, 2025

New Date:

HourTotal Outflow cfsGeneration Flow cfsSpill cfsForebay ElevationTailwater ElevationAverage Head
1 1660 614.20 526.27 87.93
2 1650 614.17 526.33 87.84
3 1660 614.12 526.28 87.84
4 1650 614.08 526.26 87.82
5 1660 614.05 526.30 87.75
6 1650 614.07 526.23 87.84
7 1670 614.23 526.27 87.96
8 1650 614.37 526.44 87.93
9 1630 614.46 526.27 88.19
10 1620 614.45 526.32 88.13
11 1630 614.44 526.31 88.13
12 1630 614.41 526.39 88.02
13 1570 614.39 526.15 88.24
14 1570 614.37 526.23 88.14
15 1570 614.35 526.25 88.10
16 1570 614.32 526.21 88.11
17 1580 614.29 526.24 88.05
18 1610 614.28 526.24 88.04
19 1580 614.25 526.20 88.05
20 1580 614.22 526.15 88.07
21 1660 614.19 526.24 87.95
22 1650 614.15 526.29 87.86
23 1630 614.11 526.26 87.85
24 1620 614.08 526.24 87.84
AVG 1623   614.25 526.27 87.99
MAX 1670   614.46 526.44 88.24
MIN 1570   614.05 526.15 87.75