HourTotal Outflow cfsGeneration Flow cfsSpill cfsForebay ElevationTailwater ElevationAverage Head
1 2739 300 2250 615.78 527.30 88.48
2 2721 300 2250 615.85 527.38 88.47
3 2739 300 2250 615.90 527.30 88.60
4 2739 615.95 527.34 88.61
5 2739 616.00 527.30 88.70
6 2739 616.06 527.28 88.78
7 2739 616.11 527.33 88.78
8 2721 616.14 527.39 88.75
9 2739 616.18 527.38 88.80
10 2829 616.21 527.47 88.74
11 2865 616.25 527.43 88.82
12 2865 616.27 527.48 88.79
13 2902 616.31 527.52 88.79
14 2902 616.33 527.45 88.88
15 2884 616.36 527.48 88.88
16 2865 616.39 527.52 88.87
17 2939 616.42 527.51 88.91
18 2902 616.44 527.44 89.00
19 2902 616.46 527.45 89.01
20 2902 616.49 527.48 89.01
21 2884 616.53 527.52 89.01
22 2902 616.56 527.45 89.11
23 2884 616.58 527.43 89.15
24 2902 616.61 527.43 89.18
AVG 2831 300 2250 616.26 527.42 88.84
MAX 2939 300 2250 616.61 527.52 89.18
MIN 2721 300 2250 615.78 527.28 88.47