US Army Corps of Engineers

Chief Joseph Dam

Tuesday September 8, 2026

New Date:

HourTotal Outflow kcfsGeneration Flow kcfsSpill kcfsForebay ElevationTailwater ElevationAverage HeadAverage Forebay ElevationAverage Tailwater Elevation
1 47.90 47.90 0.00 952.70 777.40 175.30 952.70 777.60
2 41.00 41.00 0.00 952.50 777.40 175.10 952.50 777.50
3 38.40 38.40 0.00 952.50 777.30 175.20 952.50 777.30
4 37.00 37.00 0.00 952.60 777.20 175.40 952.60 777.30
5 37.10 37.10 0.00 952.40 777.70 174.70 952.50 777.20
6 65.90 65.90 0.00 952.00 778.70 173.30 952.10 778.60
7 65.40 65.40 0.00 952.00 778.50 173.50 952.00 778.50
8 50.80 50.80 0.00 952.30 777.80 174.50 952.20 777.90
9 33.90 33.90 0.00 952.30 777.60 174.70 952.30 777.40
10 29.70 29.70 0.00 952.20 777.30 174.90 952.30 777.60
11 32.50 32.50 0.00 952.30 777.50 174.80 952.20 777.70
12 28.60 28.60 0.00 952.30 777.60 174.70 952.40 777.40
13 32.80 32.80 0.00 952.30 777.50 174.80 952.60 777.60
14 36.80 36.80 0.00 952.40 777.70 174.70 952.30 777.70
15 43.40 43.40 0.00 952.40 778.00 174.40 952.40 778.00
16 48.80 48.80 0.00 952.40 778.70 173.70 952.40 778.20
17 58.60 58.60 0.00 952.60 779.10 173.50 952.70 778.70
18 69.60 69.60 0.00 952.60 779.10 173.50 952.70 779.00
19 78.00 78.00 0.00 952.90 778.50 174.40 952.70 779.10
20 63.50 63.50 0.00 953.20 778.00 175.20 953.10 777.90
21 64.20 64.20 0.00 953.50 777.70 175.80 953.30 777.80
22 59.70 59.70 0.00 953.70 777.30 176.40 953.60 777.60
23 74.20 74.20 0.00 953.70 777.70 176.00 953.70 778.30
24 55.10 55.10 0.00 953.80 777.20 176.60 953.80 777.10
AVG 49.70 49.70 0.00 952.65 777.85 174.80 952.65 777.88
MAX 78.00 78.00 0.00 953.80 779.10 176.60 953.80 779.10
MIN 28.60 28.60 0.00 952.00 777.20 173.30 952.00 777.10