US Army Corps of Engineers

Priest Rapids Dam

Monday November 9, 2026

New Date:

HourTotal Outflow kcfsGeneration Flow kcfsSpill kcfsForebay ElevationTailwater ElevationAverage Head
1 97.50 94.95 1.54 483.15 407.48 75.67
2 93.30 90.90 1.50 482.96 407.07 75.89
3 92.10 89.77 1.45 482.86 406.47 76.39
4 66.70 64.45 1.51 483.26 405.27 77.98
5 65.40 63.18 1.55 483.26 404.17 79.09
6 59.70 57.50 1.57 483.41 404.00 79.40
7 59.10 56.88 1.59 483.48 403.85 79.63
8 58.70 56.43 1.62 483.65 403.81 79.84
9 59.00 56.69 1.67 483.88 403.86 80.02
10
11
12 59.50 56.79 2.00 484.84 403.84 81.00
13 59.60 56.78 2.10 485.10 403.87 81.23
14 60.00 57.06 2.24 485.48 403.88 81.60
15 60.50 57.40 2.43 486.03 403.95 82.08
16 60.80 57.48 2.63 486.71 403.97 82.74
17 64.70 61.03 2.88 487.43 405.00 82.43
18 152.60 122.10 29.23 486.93 411.69 75.24
19 179.10 135.31 42.49 486.29 412.38 73.91
20 179.20 135.75 42.05 485.70 412.65 73.05
21 179.00 136.10 41.50 485.05 412.82 72.23
22
23
24
AVG 89.82 79.29 9.66 484.71 406.32 78.39
MAX 179.20 136.10 42.49 487.43 412.82 82.74
MIN 58.70 56.43 1.45 482.86 403.81 72.23